First Phase 2012-13

The first phase of the refurbishment program was completed earlier this year. The following projects have been completed:

Boarding

  • Painting of approximately 50 dormitory rooms – £35’000
  • Carpeting of approximately 50 dormitory rooms – £50’000
  • Installation of sockets near each bed – £20’000 (on-going – one wing completed, 3 remaining)
  • Construction of blocks of  washrooms and wudhu khana facilities – £20’000 each x 10 = £200’000 (4 completed)
  • Renew door hinges and door closers (to meet fire regulations) – £10’000

School and Madrassah

  • External repair and painting of school building – £5’500
  • Creating new class rooms in school building – £5’000
  • Creating additional class rooms in madrassah building – £10’000
  • New ICT suite (required by Ofsted)- £10’000
  • New Science Lab (required by Ofsted) – £10’000
  • Bukhaari class carpet – £2’000
  • Library carpet – £2’000

Other work

  • CCTV cameras update (required by social services) – £13’750
  • Extra  washroom/wudhu khana/toilets facilities for men in basement – £15’000
  • Ovens and related works (required by healthy living standards) – £25’000
  • Refurbishment of phone corridor – £10’000

Phase 1 has been extended now to include:

  • painting and decoration of all corridors £15,000
  • refurbishment of main kitchen £5,000
  • renewing flooring in corridors £10,000
  • painting of ladies namaz hall £1,000
  • construction of an exclusive bathroom for students requiring medical attention

Please see other developments to view other projects which have also been completed recently.

Phase 2 – work to begin 2014 inshaa Allah

  • Construction of a small prayer area for day to day use
  • Construction of a dedicated men’s jalsa hall and conference centre